Resurfacing & Construction Division 
 
Resurfacing Friday Report
 
Zone I: Metro
July 5, 2009 - July 11, 2009
Projects Completed Metropolitan Section
Union Ave.,8th St. to Olympic Blvd.
CAC
Arlington Ave., 39th St. to Martin Luther King Jr. Blvd.
SLAC
Barlow St., Soto St. to Cornwell St.
ELAC
Cornwell St., Barlow St. to Cesar Chavez Ave.
ELAC
Beverly Green Dr., CL n/o Vidor Dr. to Pico Blvd.
WLAC
Beverly Green Dr., Roxbury Dr. to CL s/o Roxbury Dr.
WLAC
Carington Ave., National Blvd. to Palms Blvd.
WLAC
Malcolm Ave., National Blvd. to Queensland St.
WLAC
Barrington Ave., Gateway Blvd. to Marengo St.
WLAC
Cornwell St., Charlotte St. to Marengo St.
ELAC
14th St., Main St. to Broadway
CAC
 
 
Centerline Miles Paved: 1.78
Lane Miles Paved: 7.00




Weekend Projects Completed Metropolitan Section
None
 
 
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials Metropolitan Section
None
 
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.78
Total Lane Miles Paved: 7.00







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles