Resurfacing Friday Report
Zone I: Metro
May 3, 2009 - May 9, 2009
| Projects
Completed Metropolitan Section |
| Alley s/o 3rd St., Lorena St. to Concord St. |
CAC |
| Oxford Ave., 3rd St. to 6th St. |
|
| Virgil Ave., 3rd St. to 4th St. |
CAC |
| 7th St.., Mateo St. to Alameda St. |
CAC |
| Alley e/o Buckingham Rd., Santa Rosalia Dr. to Santo Tomas Dr. |
SLAC |
| 3rd Alley e/o West Bl., Santa Tomas Dr. to Alley n/o Don Diablo Dr. |
SLAC |
| Alley s/o Santa Rosalia Dr., Alley w/o Stocker St. to Marlton Ave. |
SLAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.32 |
| Lane
Miles Paved: 4.62 |
| Weekend
Projects Completed Metropolitan Section |
| Hoover St., 24th St. to Adams Blvd. |
05/03/09 |
|
| Hoover St., 20th St. to 24th St. |
05/03/09 |
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.44 |
| Weekend
Lane Miles Paved: 3.07 |
| Specials Metropolitan Section |
| None |
|
|
|
|
|
| |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved: 1.76 |
|
Total Lane Miles Paved: 7.69 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|