Resurfacing Friday Report
Zone I: Metro
March 22, 2009 - March 28, 2009
| Projects
Completed Metropolitan Section |
| Via Marisol, Monterey Rd. to Lomitas Dr. |
ELAC |
| BurkshireA ve., BrockhavenA ve. to National Blvd. |
|
| Zanja St., Lyceum Ave. to Redwood Ave. |
WLAC |
| Zanja St.., CL e/o Meier St. to Lyceum Ave. |
WLAC |
| Compton Ave., Washingon Blvd. to Adams Blvd. |
SLAC |
| Diamond St., Figueroa St. to Fremont Ave. |
CAC |
| Grande Vista Ave., Olympic Blvd. to Emery St. |
SLAC |
| Haneman St., DE e/o Rice Ave. to Nolden St. |
ELAC |
| Granada St., Holland Ave. to Avenue 50 |
ELAC |
| Hobart St., 4th St. to 6th St. |
CAC |
| |
|
| |
|
| Centerline
Miles Paved: 2.28 |
| Lane
Miles Paved: 8.69 |
| Weekend
Projects Completed Metropolitan Section |
Hoover St., Olympic Blvd. to Alvarado St. |
03/28/09 |
CAC |
| |
|
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.48 |
| Weekend
Lane Miles Paved: 2.47 |
| Specials Metropolitan Section |
| F. St., Broad Ave. to Avalon Blvd. |
03/22/09 |
HAC |
| E. St., Broad Ave. to Avalon Blvd. |
03/22/09 |
HAC |
| |
|
|
| |
|
|
| Special
Miles Paved: 0.06 |
|
Total Centerline Miles Paved: 2.76 |
|
Total Lane Miles Paved: 11.16 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|