Resurfacing Friday Report
Zone I: Metro
March 1, 2009 - March 7, 2009
| Projects
Completed Metropolitan Section |
| Figueroa St., 42nd St. to Vernon Ave. |
SLAC
|
| Virgil Ave., Temple St. to 3rd St. |
|
| Denker Ave., 79th St. to Manchester Ave. |
WLAC |
| Willoughby Ave., Gower St. to El Centro Ave.. |
CAC |
| Willoughby Ave., El Centro Ave..to Vine St. |
CAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.42 |
| Lane
Miles Paved: 5.95 |
| Weekend
Projects Completed Metropolitan Section |
La Cienega Blvd. W/Rdwy, La Tijera Blvd. to Cory Dr. |
03/01/09 |
WLAC |
| La Cienega Blvd. W/Rdwy, Cory Dr. to Thornburn St. |
03/01/09 |
|
| |
|
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.98 |
| Weekend
Lane Miles Paved: 1.83 |
| Specials Metropolitan Section |
| None |
|
|
| |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved: 2.40 |
|
Total Lane Miles Paved: 7.78 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|