Resurfacing Friday Report
Zone I: Metro
February 15, 2009 - February 21, 2009
| Projects
Completed Metropolitan Section |
| Union Pl., Beverly Bl. to 460' s/o Crown Hill Ave. |
CAC
|
| Benton Wy., 2nd St. to 3rd St. |
|
| San Pedro St., Manchester Av. to 95th St. |
SLAC |
| 17th St., Arlington A v. to 7th A v. |
CAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.45 |
| Lane
Miles Paved: 5.76 |
| Weekend
Projects Completed Metropolitan Section |
None |
|
|
| |
|
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Metropolitan Section |
| None |
|
|
| |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved: 1.45 |
|
Total Lane Miles Paved: 5.76 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None