Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
September 21, 2008 - September 27, 2008
Projects Completed Metropolitan Section
Estrella Ave., Slauson Ave. to DE s/o 59 St.
SLAC
Bonsallo Ave., Slauson Ave. to 59th Pl.
SLAC
Kansas Ave., Martin Luther King Jr. Blvd. to 40th Pl.
SLAC
Olive St., Slauson Ave. to 59th Pl.  
SLAC
82nd St., Figueroa St. to Hoover St.
SLAC
Link St., Imperial Hwy. to 116th St.
SLAC
48th St., San Pedro St. to Main St.
SLAC
47th Pl., San Pedro St. to Main St.
SLAC
36th Pl., 37th St. to Broadway
SLAC
Alley n/o Rose Ave., 6th Ave. to Dimmick Ave
WLAC
 
 
Centerline Miles Paved: 1.84
Lane Miles Paved: 6.27




Weekend Projects Completed Metropolitan Section
North Broadway, Daly St. to Pasadena Ave.
09/21/08
EAC
 
 
Weekend Centerline Miles Paved: 0.54
Weekend Lane Miles Paved: 3.24




Specials Metropolitan Section
None
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.38
Total Lane Miles Paved: 9.51







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles