|
Resurfacing Friday Report
Zone I: Metro
February 3, 2008 - February 9, 2008
| Projects
Completed Metropolitan Section |
| 77th St., Denrock Ave. to McConnell Ave. |
WLAC |
| Union Pacific Ave., Velasco St. to Grande Vista St. |
.SLAC |
| Lorena St., 8th St. to Grande Vista St. |
.SLAC |
| Berenice Ave., DE n/o Ave 43 to DE s/o Ave 39 |
EAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.29 |
| Lane
Miles Paved: 4.68 |
| Weekend
Projects Completed Metropolitan Section |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.29 |
|
Total Lane Miles Paved: 4.68 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|