Resurfacing Friday Report
Zone II: Valley
January 6 , 2008 - January 12, 2008
| Major Projects
Completed Valley Section |
| Aults Ave., Egbert St. to Sayre St. |
N/V |
| Breger Ave., DE n/o Kinbrook St. to Kinbrook St. |
N/V |
| Gretna Green Way, Montana Ave. to Goshen Ave. |
W/LA |
| Chamberlain St., DE e/o Sharp Ave. to Bartee Ave. |
N/V |
| Morena Ave., San Vicente Blvd. to CL s/o Benvenue St. |
W/LA |
Rayen St., DE e/o Ruffner Ave. to Balboa Blvd. |
N/V |
| Beck Ave., Addison St. to Riverside Dr. |
S/V |
| Bryant St., Oakdale Ave. to Penfield Ave. |
N/V |
| Auckland Ave., DE n/o Magnolia Blvd. to Magnolia Blvd. |
S/V |
| |
|
| |
|
| Centerline
Miles Paved: 2.56 |
| Lane
Miles Paved: 7.55 |
| Weekend
Projects Completed Valley Section |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Valley Section |
| None |
|
|
|
|
Total Centerline Miles Paved:
2.56 |
|
Total Lane Miles Paved: 7.55 |
1
|
Grand Total Centerline Miles Paved:
4.04 |
|
Grand Total Lane Miles Paved: 12.54 |
| Access Ramps |
| MTA Ramps |
3 |
| SRP Ramps |
0 |
| Resurfacing Ramps |
0 |
|
Access Ramps Cummulative Totals 3 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|