Resurfacing Friday Report
Zone I: Metro
January 6, 2008 - January 12, 2008
| Projects
Completed Metropolitan Section |
| 242nd Pl., Censor Ave. to President Ave. |
SLAC |
| 238th St., Western Ave. to Fulmar Ave. |
SLAC |
| Gramercy Pl., Washington Blvd. to Gramercy Park |
CAC |
| Central Ave., 32nd St. to Martin Luther King Jr. Blvd. |
SLAC |
| Framdale Ave., Vineyard Ave. to 30th St. |
SLAC |
| 19th St., Pacific Ave. to Gaffey St. |
HAC |
| Keniston Ave., Wilshire Blvd. to 400' s/o 9th St. |
CAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.48 |
| Lane
Miles Paved: 4.99 |
| Weekend
Projects Completed Metropolitan Section |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.48
|
|
Total Lane Miles Paved: 4.99
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|