Resurfacing Friday Report
ZONE II: VALLEY
June 03, 2012 - June 09, 2012
| Projects Completed Valley Section | |
| Community St., Schoenborn St. to Gothic Av. | N/V |
| Dearborn St., Gothic Av. to Monogram Av. | N/V |
| Knapp St., Gothic Av. to Monogram Av. | N/V |
| Monogram Av., Tupper St. to Calahan St. | N/V |
| Calahan St., Swinton Av. to Monogram Av. | N/V |
| Crebs Av., Tuba St. to Wilbur Av. | N/V |
| Van Nuys Bl., Chase St. to Lorne St. | N/V |
| Glenoaks Bl., Osborne Pl. to Montague St. | N/V |
| Cayuga Av., Pierce St. to Terra Bella St. | N/V |
Centerline Miles Paved: 2.44 |
|
| Lane Miles Paved: 10.31 |
|
| Weekend Projects Completed Valley Section | ||
| Sunland Bl., Sunland Pl. to Tuxford St. | |
S/V |
| |
||
| |
||
| Weekend Centerline Miles Paved: 0.76 |
||
| Weekend Lane Miles Paved: 4.41 |
||
| Specials Valley Section | ||
| None | ||
Special Miles Paved: 0.00 |
||
Total Centerline Miles Paved: 3.20 |
Total Lane Miles Paved: 14.72 |
Equipment Problems
| Large Profilers | Midsize Profilers | Small Profilers | Skiploaders |
| Pavers | Rollers | Graders | R.T. Loaders |
| Track Loaders | Backhoes | Gradals | |
|
Personnel Problems: None Other Problems: None |
|||