Resurfacing Friday Report
ZONE II: VALLEY
May 13, 2012 - May 19, 2012
| Projects Completed Valley Section | |
| Keswick St., Sunnybrae Av. to DE w/o Sunnybrae Av. | S/V |
| Sunnybrae Av., Arminta St. to DE s/o Keswick St. | S/V |
| Bassett St., Oso Av. to Fullbright Av. | S/V |
| Schoolcraft St., Delco Av. to DE w/o Delco Av. | S/V |
| Leadwell St., McLaren Av. to Royer Av. | S/V |
| Valerio St., McLaren Av. to Royer Av. | S/V |
| McLaren Av., Valerio St. to Cantlay St. | S/V |
| Cantlay St., McLaren Av. to Royer Av. | S/V |
| Wyandotte St., Fallbrook Av. to Royer Av. | S/V |
| Bassett St., Delco Av. to DE w/o Delco Av. | S/V |
| Donna Av., Oxnard St. to DE s/o Collins St. | S/V |
| Allott Av., Hatteras St. to Burbank Bl. | S/V |
| Capri Dr., Sunset Bl. to DE s/o Corsica Dr. | WLA |
| Greenbush Av., DE n/o Collins St. to DE s/o Collins St. | S/V |
Centerline Miles Paved: 2.48 |
|
| Lane Miles Paved: 7.16 |
|
| Weekend Projects Completed Valley Section | ||
| Nordhoff St., Osborne St. to Woodman Av. | |
N/V |
| |
||
| |
||
| Weekend Centerline Miles Paved: 0.29 |
||
| Weekend Lane Miles Paved: 1.66 |
||
| Specials Valley Section | ||
| None | ||
Special Miles Paved: 0.00 |
||
Total Centerline Miles Paved: 2.77 |
Total Lane Miles Paved: 8.82 |
Equipment Problems
| Large Profilers | Midsize Profilers | Small Profilers | Skiploaders |
| Pavers | Rollers | Graders | R.T. Loaders |
| Track Loaders | Backhoes | Gradals | |
|
Personnel Problems: None Other Problems: None |
|||