Resurfacing Friday Report
ZONE I: METRO
May 13, 2012 - May 19, 2012
| Projects Completed Metropolitan Section | |
| Englander St., Taper Av., to Amelia Av. | |
| 16th St., Leland St. to La Grande Tr. | |
| Allesandro St., Glendale Bl./Effie St. to Berkeley Av. | |
| Bonnie Brae St., Park Av. to Montrose St. | |
| South Park Av. N./Rdwy., East Bl. to Marcasel Av. | |
| Apex Av., Glendale Bl. to Baxter St. | |
| Waterloo St., Fargo St. to Duane St. | |
| Fries Av., F St. to C St. | |
| Anaheim St., Farragut Av. to 295' w/o Sigsbee Av. | |
| McConnell Av., Culver Bl. to Milton St. | |
Centerline Miles Paved: 2.00 |
|
| Lane Miles Paved: 8.04 |
|
| Weekend Projects Completed Metropolitan Section | ||
| None | |
|
| |
||
| |
||
| Weekend Centerline Miles Paved: 0.00 |
||
| Weekend Lane Miles Paved: 0.00 |
||
| Specials Metropolitan Section | ||
| None | ||
Special Miles Paved: 0.00 |
||
Total Centerline Miles Paved: 2.00 |
Total Lane Miles Paved: 8.04 |
Equipment Problems
| Large Profilers | Midsize Profilers | Small Profilers | Skiploaders |
| Pavers | Rollers | Graders | R.T. Loaders |
| Track Loaders | Backhoes | Gradals | |
|
Personnel Problems: None Other Problems: None |
|||