Resurfacing Friday Report
ZONE II: VALLEY
April 15, 2012 - April 21, 2012
| Projects Completed Valley Section | |
| Owensmouth Av., San Jose St. to Devonshire St. | N/V |
| Lemarsh St., Lurline Av. to De Soto Av. | S/V |
| Hatillo Av., Mayall St. to Vintage St. | N/V |
| Calvin Av., Mayall St. to Lassen St. | N/V |
| Stare St., DE e/o Calvin Av. to Calvin Av. | N/V |
| Claire Av., DE n/o Blackhawk St. to DE s/o Blackhawk St. | N/V |
| Marilla St., DE e/o Chimineas Av. to Nestle Av. | N/V |
| Labrador St., DE e/o Chimineas Av. to Nestle Av. | N/V |
| Lindley Av., Andrea CL s/o Lassen St. | N/V |
| Lassen St., Zelzah Av. to Lindley Av. | S/V |
| Merridy St., 640' w/o White Oak Av. to Zelzah Av. | N/V |
| Plummer St., White Oak Av. to Zelzah Av. | N/V |
| La Maida St., Moorpark St. to Ventura Bl. | N/V |
| Canoga Av., Victory Bl. to Sherman Way | N/V |
Centerline Miles Paved: 2.04 |
|
| Lane Miles Paved: 7.67 |
|
| Weekend Projects Completed Valley Section | ||
| Olympic Bl., Midvale Av. to Kelton Av. | |
WLA |
| Olympic Bl., Kelton Av. to Sepulveda Bl. | |
WLA |
| Canoga Av., Victory Bl. to Sherman Way | |
N/V |
| |
||
| |
||
| Weekend Centerline Miles Paved: 1.25 |
||
| Weekend Lane Miles Paved: 6.98 |
||
| Specials Valley Section | ||
| None | ||
Special Miles Paved: 0.00 |
||
Total Centerline Miles Paved: 3.28 |
Total Lane Miles Paved: 14.65 |
Equipment Problems
| Large Profilers | Midsize Profilers | Small Profilers | Skiploaders |
| Pavers | Rollers | Graders | R.T. Loaders |
| Track Loaders | Backhoes | Gradals | |
|
Personnel Problems: None Other Problems: None |
|||