Resurfacing Friday Report
ZONE II: VALLEY
April 01, 2012 - April 07, 2012
| Projects Completed Valley Section | |
| Merridy St., Vanalden Av. to Tampa Av. | N/V |
| Topeka Dr., Mayall St. to Vintage St. | N/V |
| Jumilla Av., Mayall St. to Septo St. | N/V |
| Merridy St., Jumilla Av. to DE e/o Jumilla Av. | N/V |
| Burton St., Encino Av. to Jellico Av. | N/V |
| Sesnon Bl., DE e/o Beaufit Av. to Tampa Av. | N/V |
| Colombus Av., Plummer St. to DE s/o Dearborn St. | N/V |
| Dearborn St., Columbus Av. to Columbus Av. | N/V |
| Gledhill St., Cedros Av. to Kester Av. | N/V |
| Hillrose St., Tujunga Bl. to Woodward Av. | N/V |
| Corbin Av., Saticoy St. to Sherman Wy. | N/V |
| Corbin Av., Roscoe Bl. to Saticoy St. | N/V |
| Nordhoff St., Tampa Av. to Nordhoff Wy. | N/V |
| Alley e/o Van Nuys Bl., Dickens St. to Benefit St. | S/V |
Centerline Miles Paved: 4.19 |
|
| Lane Miles Paved: 18.49 |
|
| Weekend Projects Completed Valley Section | ||
| None | |
|
| |
||
| |
||
| Weekend Centerline Miles Paved: 0.00 |
||
| Weekend Lane Miles Paved: 0.00 |
||
| Specials Valley Section | ||
| None | ||
Special Miles Paved: 0.00 |
||
Total Centerline Miles Paved: 4.19 |
Total Lane Miles Paved: 18.49 |
Equipment Problems
| Large Profilers | Midsize Profilers | Small Profilers | Skiploaders |
| Pavers | Rollers | Graders | R.T. Loaders |
| Track Loaders | Backhoes | Gradals | |
|
Personnel Problems: None Other Problems: None |
|||