Resurfacing Friday Report
ZONE I: METRO
March 18, 2012 - March 24, 2012
| Projects Completed Metropolitan Section | |
| City View St., Soto St. to St. Louis St. | EAC |
| Judson St., Cornell St. to St. Louis St. | EAC |
| Coronado St., Temple St. to Beverly Bl. | CAC |
| Fresno St., Winter St. to Malabar St. | EAC |
| Council St., Lake Shore Tr. to Belmont Av. | CAC |
| Mathew St., 1st St. to 4th St. | EAC |
| Dacotah St., Atlantic St. to DE s/o Atlantic St. | EAC |
| Romaine St., Hobart Bl. to Western Av. | CAC |
| Clinton St., Harvard Bl. to Western Av. | CAC |
| Hollister Av., Warwick Av. to Alhambra Av. | EAC |
| Mariposa Av., Romaine St. to Marathon St. | CAC |
| Lake Shore Tr., Council St. to Colton St. | CAC |
| Kingsley Dr., Franklin Av. to Hollywood Bl. | CAC |
| Hudson Av., Santa Monica Bl. to Willoughby Av. | CAC |
| San Pascual Av., San Ramon Dr. to Comet St. | EAC |
| Eagle Rock Bl., Hill Dr. to Colorado Bl. | EAC |
| Seward St., DeLongpre Av. to Santa Monica Bl. | CAC |
Centerline Miles Paved: 3.39 |
|
| Lane Miles Paved: 11.76 |
|
| Weekend Projects Completed Metropolitan Section | ||
| None | |
|
| |
||
| Weekend Centerline Miles Paved: 0.00 |
||
| Weekend Lane Miles Paved: 0.00 |
||
| Specials Metropolitan Section | ||
| None | ||
Special Miles Paved: 0.00 |
||
Total Centerline Miles Paved: 3.39 |
Total Lane Miles Paved: 11.76 |
Equipment Problems
| Large Profilers | Midsize Profilers | Small Profilers | Skiploaders |
| Pavers | Rollers | Graders | R.T. Loaders |
| Track Loaders | Backhoes | Gradals | |
|
Personnel Problems: None Other Problems: None |
|||