Resurfacing Friday Report
Zone II: Valley
July 03, 2011 - July 09, 2011
| Major Projects
Completed Valley Section |
| Falkirk Ln., Gretna Green Wy. to DE w/o Gretna Green Wy. |
WLA |
| Firth Av., DE n/o Marzella Av. to Halliday Av. |
WLA |
| Balsam Av., Thayer Av. to DE s/o Holmby Av. |
WLA |
| Balsam Av., Olympic Bl. to Lauriston Av. |
WLA |
| Louisiana Av., Beverly Glen Bl. to DE w/o Prosser Av. |
WLA |
| Sheffield Wy., Sheffield Ln. to DE s/o Sheffield Wy. |
N/V |
| Sheffield Ln., DE e/o Sheffield Wy. to DE w/o Chimineas |
N/V |
| Chimineas Av., Reseda Bl. to Eddleston Dr. |
N/V |
| Charlton Ln., DE e/o Chimineas Av. to DE w/o Chimineas Av. |
N/V |
| Hanna Av., DE n/o Elkwood St. to Elkwood St. |
N/V |
| Elkwood St., Topanga Cyn. Bl. to Glade Av. |
N/V |
| Paskenta Rd., Marinette Rd. to Chautauqua Bl. |
WLA |
| |
|
| |
|
| Centerline
Miles Paved: 1.46 |
| Lane
Miles Paved: 3.90 |
| Weekend
Projects Completed Valley Section |
| Wilshire Bl., CL e/o Comstock Av. to Comstock Av. |
|
WLA |
| |
|
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.49 |
| Weekend
Lane Miles Paved: 2.95 |
| Specials Valley Section |
| None |
|
|
| |
|
|
| |
|
|
Special Miles Paved: 0.00
|
|
Total Centerline Miles Paved: 1.95 |
|
Total Lane Miles Paved: 6.85
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|