Resurfacing & Construction Division 
 
Resurfacing Friday Report
 
Zone I: Metro
April 03, 2011 - April 09, 2011
Projects Completed Metropolitan Section
Deane St., Glendale Bl. to Edgewater Te.
ELAC
Avon Wy .,DE e/o Kensington Rd. to Inglewood Bl.
WLAC
Coolidge Pl., Coolidge Av. to DE w/o Coolidge Av.
WLAC
Mott St., 4th St. to 6th St.
ELAC
9th St., Muirfield Rd. to Rimpau Bl.
CAC
Beverly Bl. (N./Rdwy), Glendale Bl. to Witmer St.
CAC
 
 
Centerline Miles Paved: 0.76
Lane Miles Paved: 2.14




Weekend Projects Completed Metropolitan Section
Rodney Dr., Hollywood Bl. to Sunset Bl.
CAC
Sunset Bl., Virgil Av. to Vermont Av.
CAC
 
 
Weekend Centerline Miles Paved: 0.33
Weekend Lane Miles Paved: 1.65




Specials Metropolitan Section
None
 
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.09
Total Lane Miles Paved: 3.79







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles