Resurfacing & Construction Division 
 
Zone I: Metro
May 30, 2010 - June 5, 2010
Projects Completed Metropolitan Section
Washington Bl., Vermont Ave. to Normandie Ave.
CAC
 
 
Centerline Miles Paved: 0.50
Lane Miles Paved: 3.01




Weekend Projects Completed Metropolitan Section
None
 
 
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials Metropolitan Section
None
 
 
Special Miles Paved: 0.00




Total Centerline Miles Paved:0.50
Total Lane Miles Paved: 3.01







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles