Resurfacing & Construction Division 
 
Resurfacing Friday Report
 
Zone I: Metro
October 11, 2009 - October 17, 2009
<
Projects Completed Metropolitan Section
93rd St., Halldale Ave. to Denker Ave.
WLAC
94th St., Normandie Ave. to Western Ave.
WLAC
Malabar St., Sloat St. to Evergreen Ave.
ELAC
74th St., Piper Ave. to Airport Blvd.
WLAC
74th St., Piper Ave. to Piper Ave.
WLAC
Piper Ave., DE n/o 74th St. to 74th St.
WLAC
 
 
Centerline Miles Paved: 1.18
Lane Miles Paved: 3.52




Weekend Projects Completed Metropolitan Section
Washington Blvd., 6th Ave. to Crenshaw Blvd.
10/17/09
CAC
 
 
Weekend Centerline Miles Paved: 0.42
Weekend Lane Miles Paved: 2.66




Specials Metropolitan Section
None
 
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.60
Total Lane Miles Paved: 6.18







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles