Resurfacing Friday Report
Zone I: Metro
February 22, 2009 - February 28, 2009
| Projects
Completed Metropolitan Section |
| 7th Ave., Venice Blvd. to 17th St. |
CAC
|
| 7th Ave., 17th St. to Washington Blvd. |
|
| Main St., 91st St. to 99th St. |
SLAC |
| Westmount Dr., Amelia Ave. to Western Ave. |
HAC |
| Meyler St., Sepulveda Blvd. to 1st St. |
HAC |
| 253rd St., Vermont Ave. to Petroleum Ave. |
HAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.56 |
| Lane
Miles Paved: 7.09 |
| Weekend
Projects Completed Metropolitan Section |
None |
|
|
| |
|
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Metropolitan Section |
| None |
|
|
| |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved: 1.56 |
|
Total Lane Miles Paved: 7.09 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|