Resurfacing Friday Report
Zone I: Metro
December 7, 2008 - December 13, 2008
| Projects
Completed Metropolitan Section |
| Almont St., Maycrest Ave. to Stillwell Ave. |
EAC |
| Almont St., Stillwell Ave. to Barrett Rd. |
|
| Phelps Ave., Lynnfield St. to Lombardy Blvd. |
EAC |
| Ladd Ave., Lombardy Blvd. to DE W/o Mallory St. |
EAC |
| Kimball St., Lombardy Blvd. to DE W/o Lombardy Blvd. |
EAC |
| Tipton Te., Buena Vista Te. to DE S/o Buena Vista Te |
EAC |
| Bedilion St., Okell Dr.to Bowman Blvd. |
EAC |
| Latona Ave., Ave 43 to DE S/o Ave 43 |
EAC |
| Jasper St., Verdemour Ave. to DE W/o VerdemourAve |
EAC |
| Carter Dr., Bedilion St. to DE S/o Bedilion St. |
EAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.67 |
| Lane
Miles Paved: 3.04 |
| Weekend
Projects Completed Metropolitan Section |
Culver Blvd., CL E/o Corinth Ave. to Inglewood Blvd. |
12/07/08 |
W.L.A.C. |
| |
|
|
| |
|
|
| Weekend
Centerline Miles Paved: 0.57 |
| Weekend
Lane Miles Paved:2.52 |
| Specials Metropolitan Section |
| None |
|
|
| |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved: 2.24 |
|
Total Lane Miles Paved: 5.56 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None