Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
December 7, 2008 - December 13, 2008
Projects Completed Metropolitan Section
Almont St., Maycrest Ave. to Stillwell Ave.
EAC
Almont St., Stillwell Ave. to Barrett Rd.
EAC
Phelps Ave., Lynnfield St. to Lombardy Blvd.
EAC
Ladd Ave., Lombardy Blvd. to DE W/o Mallory St.
EAC
Kimball St., Lombardy Blvd. to DE W/o Lombardy Blvd.
EAC
Tipton Te., Buena Vista Te. to DE S/o Buena Vista Te
EAC
Bedilion St., Okell Dr.to Bowman Blvd.
EAC
Latona Ave., Ave 43 to DE S/o Ave 43
EAC
Jasper St., Verdemour Ave. to DE W/o VerdemourAve
EAC
Carter Dr., Bedilion St. to DE S/o Bedilion St.
EAC
 
 
Centerline Miles Paved: 1.67
Lane Miles Paved: 3.04




Weekend Projects Completed Metropolitan Section
Culver Blvd., CL E/o Corinth Ave. to Inglewood Blvd.
12/07/08
W.L.A.C.
 
 
Weekend Centerline Miles Paved: 0.57
Weekend Lane Miles Paved:2.52




Specials Metropolitan Section
None
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.24
Total Lane Miles Paved: 5.56







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 