Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
October 5, 2008 - October 11, 2008
Projects Completed Metropolitan Section
Lilac Te., Lookout Dr. to Stadium Way
EAC
Lilac Pl., Innes Ave. to Elysian Park Ave.
EAC
Evadale Dr., DE n/o Paige St/Elderbank Dr. to Paige St/Elderbank Dr.
EAC
75th St., Hoover St. to Vermont Ave.
SLAC
Elderbank Dr., Evadale Dr/Paige St. to Latrobe St.
EAC
75th St., Figueroa St. to Hoover St.
SLAC
Naomi Ave., 40th Pl. to 41st St.
SLAC
Naomi Ave., 32nd St. to 40th Pl.
SLAC
 
 
Centerline Miles Paved: 1.79
Lane Miles Paved: 5.26




Weekend Projects Completed Metropolitan Section
None
 
 
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials Metropolitan Section
None
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.79
Total Lane Miles Paved: 5.26







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles