Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
August 10, 2008 -August 16, 2008
Projects Completed Metropolitan Section
85t St., Raymond Ave. to Norrnandie Ave.
SLAC
102nd St., 50' w/o Main St. to Broadway
SLAC
101st St., Broadway to Olive St.
SLAC
12th Ave., 23rd St. to DE s/o 23rd St.
CAC
23rd St., 10th Ave. to Bronson Ave.
CAC
9th Ave., 23rd St. to DE s/o 23rd St.
SLAC
9th Ave., DE n/o 25th St. to Adams Blvd.
CAC
2nd Ave., Pico Blvd. to Venice Blvd.
CAC
15th St., Arlington Ave. to 3rd St.
CAC
Alley w/o Garth Ave., Sawyer Ave. to Guthrie Ave.
CAC
Dalton Ave., 39th St. to Martin Luther King Jr. Blvd.
SLAC
Alley e/o Crenshaw Blvd., 78th Pl. to DE s/o 78th Pl.
SLAC
 
 
Centerline Miles Paved: 1.60
Lane Miles Paved: 4.99




Weekend Projects Completed Metropolitan Section
Vermont Ave., Pico Blvd. to Venice Blvd.
8/10/08
SLAC
Hillhurst Ave., Prospect Ave. to Hollywood Blvd.
8/10/08
CAC
 
 
Weekend Centerline Miles Paved: 0.44
Weekend Lane Miles Paved: 2.28




Specials Metropolitan Section
None
 
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.04
Total Lane Miles Paved: 7.27







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 