Resurfacing Friday Report
Zone I: Metro
June 15, 2008 - June 21, 2008
| Projects
Completed Metropolitan Section |
| Fairfax Ave., Venice Blvd. to Apple St. |
CAC |
| |
|
| |
|
| Centerline
Miles Paved: 0.27 |
| Lane
Miles Paved:1.49 |
| Weekend
Projects Completed Metropolitan Section |
| Fairfax Ave., Washington Blvd. to Smiley Dr. |
06/21/08 |
SLAC |
| |
|
|
| Weekend
Centerline Miles Paved: 0.22 |
| Weekend
Lane Miles Paved:1.20 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
0.49 |
|
Total Lane Miles Paved: 2.69 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|