Resurfacing Friday Report
Zone I: Metro
June 1, 2008 - June 7, 2008
| Projects
Completed Metropolitan Section |
| Manhatten Pl., 8th St. to Olympic Blvd. |
CAC |
| Mariposa Ave., 8th St. to Olympic Blvd. |
CAC |
| |
|
| |
|
| Centerline
Miles Paved: 0.67 |
| Lane
Miles Paved: 2.21 |
| Weekend
Projects Completed Metropolitan Section |
| Melrose Ave., Gamer St. to Fairfax Ave. |
06/01/08 |
WLAC |
| |
|
|
| Weekend
Centerline Miles Paved: 0.47 |
| Weekend
Lane Miles Paved:2.30 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.14 |
|
Total Lane Miles Paved: 4.51 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None