Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
May 11, 2008 - May 17, 2008
Projects Completed Metropolitan Section
Saratoga St., 2nd St. to 4th St.
CAC
Alta St., Pomona St. to Emma St.
ELAC
Emma Ave., Sierra St. to Alta St.
ELAC
Aylesworth Pl., Eastlake Ave. to Hancock St.
ELAC
Minnesota St., Gates St. to Johnston St.
ELAC
Dundas St., Ganahl St. to Wabash Ave.
ELAC
Lara St., Ganahl St. to Dobinson St.
ELAC
41st St., Main St. to Broadway
SLAC
White House Pl., DE e/o Bimini Pl. to Bimini Pl.
CAC
 
 
Centerline Miles Paved: 1.18
Lane Miles Paved: 3.31




Weekend Projects Completed Metropolitan Section
Beverly BI., La Cienega Blvd. to CL W/o La Cienega Blvd.
05/17/08
CAC
 
Weekend Centerline Miles Paved: 0.13
Weekend Lane Miles Paved:0.62




Specials Metropolitan Section
None.
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.31
Total Lane Miles Paved: 3.93







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 