Resurfacing Friday Report
Zone I: Metro
March 30, 2008 - April 5, 2008
| Projects
Completed Metropolitan Section |
| 252nd St., Frampton Ave. to CL W/o Western Ave. |
HAC |
| 253rd St., Frampton Ave. to CL W/o Western Ave. |
HAC |
| |
|
| |
|
| Centerline
Miles Paved: 0.92 |
| Lane
Miles Paved: 2.76 |
| Weekend
Projects Completed Metropolitan Section |
| Figueroa St., Q St. to Pacific Coast Hwy. |
04/05/08 |
HAC |
| |
|
|
| Weekend
Centerline Miles Paved: 0.26 |
| Weekend
Lane Miles Paved: 1.66 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.18 |
|
Total Lane Miles Paved: 4.42 |
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None