Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
March 9, 2008 - March 15, 2008
Projects Completed Metropolitan Section
Gaffey St., Anaheim St. to 2000' s/o Anaheim Sf.
HAC
Glendale Bl. W/Rdwy, Hyperion Av. to Glendale Bl. E/Rdwy @ 5 Fwy.
CAC
 
 
Centerline Miles Paved: 0.62
Lane Miles Paved:3.78




Weekend Projects Completed Metropolitan Section
6th St., Alvarado St. to Carondolet St.
03/15/08
CAC
 
Weekend Centerline Miles Paved: 0.28
Weekend Lane Miles Paved: 1.40




Specials Metropolitan Section
None.
Special Miles Paved: 0.00




Total Centerline Miles Paved: 0.90
Total Lane Miles Paved: 5.18







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 