|
Resurfacing Friday Report
Zone I: Metro
January 27, 2008 - February 2, 2008
| Projects
Completed Metropolitan Section |
| Walgrove Ave., Palms Blvd. to Venice Blvd. |
WLAC |
| Zanja St., Walgrove Ave. to Lincoln Blvd. |
WLAC |
| 80th St., Averstone Ave. to Emerson Ave. |
WLAC |
| EI Manor Ave., 80th St. to 80th Pl. |
WLAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.63 |
| Lane
Miles Paved: 5.00 |
| Weekend
Projects Completed Metropolitan Section |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.63
|
|
Total Lane Miles Paved: 5.00
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|