|
Resurfacing Friday Report
Zone I: Metro
January 13, 2008 - January 19, 2008
| Projects
Completed Metropolitan Section |
| Hobart Blvd., Fountain Avo to Santa Monica Blvd. |
WLAC |
| Kenmore Ave., Hollywood Blvd. to Fountain Ave. |
WLAC |
| Wilton PI., Pico Blvd. to Venice Blvd. |
CAC |
| Elanita Dr., 19th St. to Patton Ave. |
HAC |
| 227th St., DE E/o Halldale Ave. to Western Ave. |
SLAC |
| |
|
| |
|
| Centerline
Miles Paved: 1.83 |
| Lane
Miles Paved: 5.61 |
| Weekend
Projects Completed Metropolitan Section |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials Metropolitan Section |
| None. |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.83
|
|
Total Lane Miles Paved: 5.61
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|